Over the last few months you may have noticed that there has been some construction going on around our building. In fact, we are adding a new sanctuary and will be adding some classrooms as well. We are excited about what God is doing here at Bible Baptist and want to share it with everyone here on this page. We will continue to update this page with where the building project stands. (We are really close to being done, actually...)

Current Status of the building project is:

 

  • Hard to believe we've been in our new sanctuary for 5 weeks now....
  • Primary and Beginners class is erected. Needs spaculling and paint
  • A new mic has been purchased and donated for the pastor.
  • The teen Sunday School room is erected. Still needs spaculing and paint.
  • October 24, 2009 - Dedication Service of the New Sanctuary!!!!
  • The money for new mics have been donated.
  • Beginning construction on the Sunday School rooms in the old sanctuary.
  • Sound Booth has been built!!!!
  • Audience listening devices have arrived.
  • Seats for the musicians have been refinished and upholstered
  • New seats for the pastor and deacon have been bought
  • Small decorative accents added to the sanctuary.
  • Chairs arrived!!!
  • All the last few things have been done with the lights and heating
  • Final inspections passed!!!! The building is ours!!!!
  • Chairs are set to arrive the 2nd week of September. :( We were hoping for the 1st of September.
  • Last few things that need done are: heating hooked up to the propane & the dimmer control center for the lights finished. Both the heating/cooling & the electric need final inspections then we can have the building final inspection done!
  • Carpet has been installed!!
  • Carpet is being installed on Monday!!
  • PA has been tested and sounds good!
  • Installed projector mount and took projector out of box but it has to be sent back to the manufacturer to be fixed... :(
  • Flown speakers above the stage in their permenant mounted position.
  • PA equipment has arrived!!
  • Rock wall has been installed in the foyer
  • Tile has been laid in the foyer
  • Stage doors are completely done
  • Stage doors are being stained tonight!
  • Ran speaker and projector wire through conduit in the cealing
  • Ran microphone wire for the piano under the stage...
  • Done painting the sanctuary!
  • The paint has arrived!
  • The sanctuary stage doors have arrived and been installed. The mainentrance doors and doors to the old church building aren't in yet. :( (August 11th is the expected arrival date...)
  • Carpet is scheduled to be installed on Autgust 17th
  • The foyer has been primed and painted!
  • Sweetwater has received the check from the bank and have allocated the equipment. The speakers are on back order... :(
  • We have recieved the ok from the bank to order the new sound equipment!!
  • Drywall is done. Spackling has started
  • Sanctuary entrance has been moved
  • The carpet company has came and taken measurments. We have a quote in hand!
  • We have decided to move the entrance to the sanctuary so that it is centered
  • Drywall has started to go up!!
  • The electrician came back to add more outlets.
  • Stage, ramp & stage access rooms have been built
  • Heating and cooling units have been completed and have passed inspection!
  • We are looking at several different types of chairs for the sanctuary
  • Heating & cooling units are just about done and we will be having them inspected. Hopefully this week
  • The rough in on the electric has passed inspection
  • Audio snake has been installed.
  • The steeple has been installed!
  • The electric rough in is complete!
  • The steeple has arrived!
  • The heating & cooling installation has begun.
  • Concrerte has been poured for the handicapped parking as well as the sidewalk.
  • Drywall has arrived.
  • The lights and outlets are being installed.
  • The roof is installed.
  • The siding (or shell) is being put on.
  • The rafters have been hung and are being held in place by cables.
  • The frame has been erected!!
  • God's building a church!